You are here:
PacLII >>
Databases >>
Court of Appeal of Vanuatu >>
2021 >>
[2021] VUCA 35
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Download original PDF
Tefeke v Vanuatu Project Management Unit [2021] VUCA 35; Civil Appeal Case 362 of 2021 (14 May 2021)
IN THE COURT OF APPEAL OF THE REPUBLIC OF VANUATU (Civil Appellate Jurisdiction) | Civil Appeal Case No. 21/362 CAC/CIVA |
BETWEEN: | MATARAU TEFEKE Appellant |
AND: | VANUATU PROJECT MANAGEMENT UNIT First Respondent |
AND: | THE GOVERNMENT OF THE REPUBLIC OF VANUATU Second Respondent |
Coram: Hon. Chief Justice Vincent Lunabek
Hon.Justice Raynor Asher
Hon.Justice Oliver Saksak
Hon Justice Dudley Aru
Hon.Justice Viran M Trief
Hon.Justice Richard White
Counsel: Mr John Malcolm for the appellant
Mr Sammy Aron for the respondents
Date of Hearing: 5th May 2021
Date of Judgment: 14th May 2021
JUDGMENT
__________________________________________________________________________________
Introduction
- This appeal is against an award made in the Supreme Court on 5th February 2021 whereby the Government was found to be liable for:
- (a) Payment of VT2,141,820 as royalties calculated at the rate of 40% of the 35,697 cubic metres of dredged material, and
- (b) Payment of VT5,354,550 for the same volume of dredged material at the rate of VT150 per cubic metre (as aggregate payment).
Relevant Facts
- On 12th February the Second Respondent through its Ministry of Infrastructure and Public Utilities entered into an agreement with the custom
landowners of the South Paray Wharf site who are family Kalpram, Tvekot and descendants,Matarau Tefeke and the community and people
of Ifira Tenuku.
- The agreement set out the terms and conditions for the application of resources to construct the Domestic Wharf facilities by Ifira
Ports and Development Services. It also set out the process and plans for long term access to the wharf by the public and for the
management of the South Paray wharf through creation of an appropriate entity.
- On 21st October 2016 a further agreement was executed between the Second Respondent, the Commissioner of Mines and the custom-landowners.
- That agreement was for the purposes of:
- Acknowledging the consent of the declared land owners to dredging and use of aggregate material from land owned by them;
- Recording the responsibilities of the Vanuatu Project Management (VPMU), (First Respondent);
- Ensuring the work carried out was in accordance with the Quarry Permit, issued;
- Recording the allocation of building materials to the project by the custom owners; and
- Setting out the arrangements for the agreed compensatory payments to the custom landowners by the Second Respondent;
- Schedule 1 of the agreement set out the payments to be made to the custom landowners in the following manner:
“1. Payment for aggregates to custom landowners shall be in the following manners:
- Total amount of aggregates extracted and used by the Government in the construction of the South Paray wharf facility to be calculated
and confirmed by Commissioner of Mines;
- Custom Land Owners to verify and check the total amount of aggregates used as provided by Commission of mines and to agree;
- Commissioner of mines to the calculate total value of aggregates in vatu and current rate under the Quarry Act and to provide the
calculation to the VPMU and Custom Land Owners;
- Payment arrangements for aggregates to Custom Landowners to be formulated, along with agreed calculations by all parties, to be agree
and completed in a series of formal meetings, the first meeting to be held within 30 days of the signing of this Agreement
- Payment for Royalties shall be done in the following manner:
- Total royalties payable by the Quarry Permit Holder to the Custom Land Owners, upon confirmation by the Commissioner of Mines, in
arrears to the Custom Land Owners at agreed regular intervals, at the rate prescribed by the Commissioner of Mines and in compliance
with the Quarry Permit issued and stipulated in the Quarry Permit Act.”
6. By 27th July 2017 the VPMU Manager had recorded that 35,697 cubic metres of aggregates had been dredged and used for the Wharf Project.
- The Second Respondent has not made payments under the agreements.
- The appellant filed proceeding against the First and Second Respondents claiming the sum of VT178,784,850 for royalty payments at
September 2017 VT50,000,000 for March, June and September 2018 and VT28,485,000 for December 2018, damages for breach of contract,
or in the alternative, for theft/ conversion and quantum meruit.
The Decision
- The primary Judge in the Supreme Court held that the appellants were entitled to VT2,141,820 as royalties and VT 5,354,550 for the
aggregates.
- First the Judge awarded VT2,141,820 in royalties to the custom land owners based on the evidence of the then Acting Commissioner of
Mines, Mr Rakau who calculated the rate at time which was VT 150 per cubic metre, and in accordance with the terms of the agreement.
- Second, the Judge refused to award the rate of VT5,000 for aggregates proposed by Mr Sope in his sworn statement. This amount was
proposed as a result of a comparison between the rates of VT6,000 – VT7,000 payable to the Fletcher Construction Limited for
aggregates quarried from quarries at Eratap and Mele.
- The Judge did not consider awarding a lower sum of VT4,000 per cubic metre of aggregates which the appellant argued was accepted by
the Attorney General.
The Appeal
- The appellant appealed those findings and decision on one ground namely that the Judge had erred in setting a minimum level retroactively.
Submissions
- The appellant submitted that the Judge was wrong in applying the VT150 rate for royalties to assess the amount payable to the custom
land owners for aggregates.
- The appellant submitted the correct rate the Judge should have adopted and awarded should have been the VT5,000 per cubic metre as
proposed by Mr Sope or the VT4,000 as said to have been admitted by the Respondent’s Solicitors.
Discussion
- The appellant accepted the Judge’s decision that VT150 per metre was the royalty rate at the time based on 40% of the 35,697
cubic metres of the dredged materials.
- The appellant challenged the VT150 per cubic metre set for aggregates.
- In deciding the minimum rate of aggregate the Judge said at [35]:
“there is no novation or variation of the original Agreement as to the manner in which the rate of payment aggregates used was
to be calculated. To set the rate at anything other than VT150 per cubic metre would be to violate the terms of the Agreement reached
by the Parties. The Claimant is bound by what was agreed, namely that the vote is to be fixed by the Minister of Mines, which he
has done. Further, the rate which the Minister set is not out of proportion with other rates at the time. The claimant is not entitled
to any more than VT 150 per cubic metre of aggregates.”
- Clause 8 (c) of the Agreement states:
“The total value and amount of extracted materials must be clearly calculated and shown to the Custom Land Owners by the Commissioner
of Mines and the arrangement to pay such total amount as outlined in the Schedule of this Agreement. This is to be called “payment
for aggregates.”
- Schedule 1 (c) of the Agreement states:
“(c) Commissioner of Mines to then calculate total value of aggregates in vatu at the current rate used under the Quarry Act
and to provide the calculation to the VPMU and Custom Land Owners.”
- The Judge had in evidence before him the letter dated 28 May 2018 written by the Commissioner of Mines to the VPMU (First Respondent).
That letter sets out the rates of both royalties and aggregates at VT150 per cubic metre and confirms this was the “practiced”
minimum rate at the time.
- The Judge recorded at [22] of the Judgment that:
“on 28th May 2008, VPMU received from the Commissioner of Mines the valuation of extracted material at the rate of VT 150 per cubic metre.”
- The letter of 28 May 2018 was made in accordance with Clause 8 (c) of the Agreement read together with Clause 1(c) of Schedule 1 of
the Agreement.
- Those steps and actions were taken in accordance with the provisions of the Quarry Act.
- We are not persuaded the Judge was wrong in applying the minimum rate for aggregate payment at VT 150 per cubic metre. We agree with
the trial judge’s interpretation of the plain words of the Agreement.
- Moreover, the agreement must be construed against the background that the payment was for raw aggregate in a rough state by the lagoon,
which would require considerable expenditure to remove to a place where it could be sold in a reasonable condition, and then the
retailer would want a margin. Plainly it would make no sense if the retail rate was intended to be paid to the Appellants, with
all those costs still ahead. They would thereby get a massive unearned and plainly unintended bonus.
- The Judge had correctly construed the relevant provisions of the Agreements and was satisfied on the evidence the provisions of the
Quarry Act had been complied with. We find no error in the Judge’s decision.
The Result
- This appeal is therefore dismissed.
- The appellant will pay the respondent’s costs fixed at VT 40,000.
DATED at Port Vila this 14th day of May, 2021
BY THE COURT
Chief Justice V. Lunabek
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.paclii.org/vu/cases/VUCA/2021/35.html