PacLII Home | Databases | WorldLII | Search | Feedback

High Court of Solomon Islands

You are here:  PacLII >> Databases >> High Court of Solomon Islands >> 1999 >> [1999] SBHC 113

Database Search | Name Search | Recent Decisions | Noteup | LawCite | Help

Kiere v Han Sin Construction Ltd [1999] SBHC 113; HC-CC 078 of 1999 (24 November 1999)

HIGH COURT OF SOLOMON ISLANDS

CIVIL CASE CASE NUMBER 078 OF 1999

<

BARBARA KIERE AND ELLISON KIERE

v

class="MsoNormal" aal" align="center" style="text-align:center; margin-top:1; margin-bottom:1">HAN SIN CONSTRUCTION LIMITED

HIGH COURT OF SO ISLANDS
(PALMER J.)
CIVIL CASE NUMBER 078 OF 1999

HEARING: 8 OCTOBER 1999
JUDGEMENT: 24 NOVEMBER 1999

C. ASHLEY FOR THE PLAINTIFINTIFFS
A. RADCLYFFE FOR THE DEFENDANT

PALMER J.: The Plaintiff, Barbara and Ellison Kiere are wife and husband. They entered into a Deed of Sale (hereinafter referred to as "the Deed") with Han Sin Construction Limited (hereinafter to as "Han Sin") for the sale of a block of land within Parcel Number 191-011-50. The fixed-term estate in the said Parcel vas owned by Han Sin. Their plan was to have the said land subdivided so that title can vest in the Plaintiffs in respect of that part of the land, the subject of the Deed, when the purchase price had been completed. That Deed was dated 9 October 1999.

Th description of the area orea of land the subject of the Deed is not in dispute. It is covered under Clause 1 of the Deed. It is also not in dispute that an incomplete residential building was still in the process of being completed on the said portion of land at the time of signing of the Deed (Clause 2). The purchase price of $250,000-00 is clearly stated in Clause 3. Clause 4 of the Deed not only specified what the deposit was to be, ($70,000-00), but acknowledged it had been paid at the time of signing of the Deed. Sub-clause 4.1 required inter alia, payment of first instalment of $55,000-00 on completion of building. Sub-clause 4.2 provided for payment of the balance ($125,000-00) within two years from date of payment of $55,000-00. Clause 6 provided for the rental payments received to be shared equally between the parties and for the half share of the Plaintiffs to be deducted towards payment of the balance of $125,000-00. This arrangement was to be reviewable after every six months.

The residential building on the said property was completed on or about 15 December 1998 (see affidavit of Ellison Kiere filed 8 October 1999 Exhibit "EK 19" at paragraph 3) and put out for rent on or about 22nd December 1998. Payment of the first instalment of $55,000-00 fell due on or about the same date (22nd December 1998). Plaintiffs however, have only paid up $30,000-00 of that amount. They had failed accordingly to comply fully with Sub-clause 4.1; $25,000-00 remained outstanding. There had thus been partial compliance. This is not disputed by the Plaintiffs. By letter dated 12 January 1999, the Defendant through its Director, Lydia Yeo, gave notice of intention to terminate the Deed (a copy of said letter is annexed to affidavit of Lydia Yeo filed 8 October 1999). Shortly thereafter, by letter dated 1 February 1999, the Respondent purported to terminate the Deed by having a cheque for the sum of $100,000-00 paid to the Plaintiffs; being refund of part of the purchase price paid up to that point of time.

The PThe Plaintiffs now come to Court seeking inter alia, an order for specific performance of the Deed, primarily on the ground that breach of Sub-clause 4.1 did not entitle the Defendant to have the Deed terminated; merely to sue for damages. The Defendant argue [sic] on the other hand, it was entitled to have the Deed terminated for breach of Sub-clause 4.1.

THE ISSUE:

The issue which arises for determination turns on simple contractual principles, whether Sub-clause 4.1 is a condition or a warranty. A breach of a condition will entitle the innocent party to treat himself as discharged from further performance under a contract and to claim damages for loss sustained by the breach (see Chitty on Contracts 26th Edition paragraphs 787 and 1727). The case authority Milichamp and Others v. Jones [1982] 1 W.L.R 1422, relied on by learned Counsel for the Defendant, pertained to the issue of breach of a condition (payment of deposit) which entitled a vendor to treat the contract as discharged and to sue for damages. A breach of a warranty on the other hand does not entitle him to treat himself as discharged.

At paragraph 794 of Chitty on Contracts (Ibid), the learned Author states:

"In the modern law, the reason why a breach of a condition entitles the innocent party to treat himself as discharged has been said to be that conditions "go so directly to the substance of the contract that their non-performance may fairly be considered by the other party as a substantial failure to perform the contract at all" (Wallis, Son and Wells v. Pratt & Haynes [1911] UKLawRpAC 21; [1910] 2 K.B. 1003, 1012). And the reason why any breach of condition has this effect has been put on the ground that the parties are to be regarded as having agreed that any failure of performance, irrespective of the gravity of the event that has in fact resulted from the breach, should entitle the other party to elect to put an end to all primary obligation of both parties remaining unperformed (Photo Production Ltd v. Securicor Transport Ltd. [1980] UKHL 2; [1980] A.C. 827)."

The learned Author then went on to explain how a condition may be differentiated in a contract:

lass="MsoNormal" sal" style="margin-left:36.0pt;tab-stops:112.5pt 222.75pt right 464.5pt; margin-top:1; margin-bottom:1">"The parties may, by express words or by implication of law, agree that a particular stipulation is to be a condition of their contract. But they may also be held to have done so by necessary implication arising from the nature, purpose and circumstances of the contract, and in this respect "There is no way of deciding that question except by looking at the contract in the light of the surrounding circumstances, and then making up one's mind whether the intention of the parties, as gathered from the instrument itself, will best be carried out by treating the promise as a warranty sounding only in damages, or as a condition precedent by the failure to perform which the other party is relieved of his liability" (Bentsen v. Taylor, Sons & Co. [1893] UKLawRpKQB 122; [1893] 2 Q.B. 274, 281)."

SUB-CLAUSE 4.1 A CONDITION OR WARRANTY?

class="MsoNormal" sal" style="tab-stops:112.5pt 222.75pt right 464.5pt; margin-top:1; margin-bottom:1">Sub-clause 4.1 dea1 deals specifically inter alia, with payment of a specific amount as part of the purchase price, at a particular point of time. It provides that the sum of $55,000-00 was to be paid by the time the residential building was completed and before the residential building was put out for rent. Sub-clause 4.2 in turn provided for the payment of the remainder within a period of two years from date of payment of $55,000-00. The period of two years therefore was anticipated to run from the date of completion of the building and before it was put out for rental. In the circumstances of this case, it would be around 22nd December 1998 and to expire around 22nd December 2000. That would have been the time span anticipated under the Deed for the Plaintiffs to complete payment of the remainder of the purchase price; $125,000-00. The effect is this, provided the $55,000-00 was paid on due date, the Deed would have been enforceable against the Defendant right up to December 2000. Looked at from this perspective, there is no way the failure to pay, $55,000-00 can be regarded as a condition which entitles the Defendant to treat itself as discharged from further performance of the Deed. I am not satisfied it can be said the breach of Sub-clause 4.1 goes so directly to the substance of the Deed that its non-performance may fairly be considered by the Defendant as a substantial failure to perform the Deed at all. As at time of breach the Plaintiffs had paid $100,000-00 towards the purchase price. This meant not the full amount of $55,000-00 was outstanding as on 22nd December 1998; only part of it, $25,000-00. It is not correct therefore to say the Plaintiffs had not complied with Sub-clause 4.1. There had actually been partial compliance. But even if they had managed to comply with Sub-clause 4.1, they would not have been required to pay up on the balance until December 2000. It wasn't the case therefore where the payment of $55,000-00 was so vital to the performance of the contract, or went to the root of performance of the Deed such that further performance was not possible. It covered only a portion of the Deed. A failure on the part of the Plaintiffs to pay that part of the purchase price therefore, cannot in my respectful view be regarded as a condition, a crucial term in the Deed, breach of which entitles the Defendant to have the Deed terminated. The partial breach committed by the Plaintiff cannot under ordinary contractual principles be regarded as amounting to a repudiatory breach of the Deed. I find the words of the Earl of Selborne L.C. in Mersey Steel and Iron Co. v. Naylor, Benzon & Co. (1884) 9 App.Cas. 434 at page 441 so apposite to the circumstances of this case:

"I cannot ascribe to their [the Plaintiffs'] conduct, under these circumstances, the character of a renunciation of the contract, a repudiation of the contract, a refusal to fulfil the contract."

I am not convinced nor satisfied, the partial breach committed by the Plaintiffs indicate an intention on their part to throw up the contract altogether, so as to set the Defendant free. The evidence couldn't be any clearer. The Plaintiffs acknowledged they did not fully comply with Sub-clause 4. 1, but made clear where reason for that failure lie. Basically they needed more time to have their loan application processed and approved. They intended to comply with the terms of the contract and maintained that position in spite of their failure to pay the full amount of $55,000-00 on the due date. The Director of the Defendant, Lydia Yeo was aware of this (see Exhibit "EK 6" annexed to the affidavit of Ellison Kiere filed 4th March 1999). The loan application of the Plaintiffs for the sum of $150,000-00 was subsequently approved on or about 20 January 1999 (see Exhibit "EK 3" of same affidavit of Ellison Kiere). That would not only have paid for the remaining $25,000-00, but also for the balance of $125,000-00, which would have meant the time period stipulated in the Deed would have been shortened greatly to the benefit of the Defendant.

I accept the Defendant was not obliged to accept the reason given by the Plaintiffs for the delay in payment of the balance of $25,000-00. Unfortunately, that did not give the Defendant right to turn around and seek to have the Deed terminated. The Defendant's remedy lies only in a claim for damages. The effect of this meant the Deed was still on foot and the parties obliged to perform their obligations where applicable. In conclusion, I find Sub-clause 4.1 to be a warranty and that its breach did not amount to repudiatory breach that would entitle the Defendant to have the Deed terminated.

class="MsoNormal" sal" style="text-align:justify; margin-top:1; margin-bottom:1">FURTHER PERFORMANCE OF THE DEED

lass="MsoNormal" sal" style="margin-top: 1; margin-bottom: 1">Despite its breach, tch, the Deed was capable of being performed and the Plaintiffs were right in demanding that its terms be complied with. There is no evidence to suggest the Plaintiffs did not acknowledge they owed the Defendant the sum of $25,000-00 as at 22nd December 1998. Even if the Plaintiffs had not paid the sum of $55,000-00 by date of completion of the building, as provided for in Sub-clause 4.1, that would not have affected the further performance of the Deed. All it would have meant would have been that all rental payments received for rental of that house (Clause 6 of the Deed) would have gone into the pocket of the Defendant alone without any being apportioned to the Plaintiffs. In this instance, $30,000-00 of the $55,000-00 had been paid, as at time of completion of the building and before it was rented out. That comes to approximately 54 % of $55,000-00. Rental payments received in respect of the property accordingly should be apportioned on a pro rata basis; that is if the rental for the property was for $3,850-00 per month the Plaintiffs would only be entitled to an amount which is 54% of half of that amount ($3,850-00 ¸ 2 X 54% = $1,039.50). In my respectful view, the rate of 54% of half the amount of the rental received for the said property should apply until the balance of $25,000-00 is paid, plus any damages which the Defendant might claim in respect of the said breach.

THE FINDINGS OF THE COURT:

lass="MsoBodyText"Text" style="margin-top: 1; margin-bottom: 1">I find there had been wrongful repudiation of the Deed by the Defendant.hat extent, the Plaintiffs are entitled to damages. Ats. At the same time I find the Plaintiffs only partially complied with Sub-clause 4.1 of the Deed. The Defendant in turn would be entitled to its claim for damages in respect of that partial breach.

It was suggestedested the remedy for specific performance should not be granted in view of the breach committed by the Plaintiffs in that they did not come with clean hands. Whilst that may be true, the partial breach committed is fully compensatable in damages. In other words, damages would be an adequate remedy. That would adequately address the partial breach complained of by the Defendant. Secondly, that breach did not give the Defendant the right to repudiate the Deed, which meant the Defendant too had acted contrary to the terms of the Deed. That in my respectful view balances out any injustices which might have been suffered by the Defendant as a result of the partial breach committed by the Plaintiff.

The Defendant is obliged to perform its part of the bargain, in particular, the requirements of subdivision and registration stipulated in Clause 8 of the Deed. The Plaintiffs have until December 2000 to come up with the remainder of the money currently owing.

THE COUNTER-CLAITHE DEFENDANT

In the counter-claim of the Defendant, one of rders sought was for the Plaintiffs to vacate the property and remove their furniture.ture. What must be understood by the parties is that the Deed is still on foot and therefore whatever rents had been received to date must be accounted for in the manner stated in this judgment, until the balance of $25,000-00 is paid. Only when that had been done will the Plaintiffs be entitled to a half share of the rent, subject of course to whatever mutual arrangements (if any), may be entered into by the parties hereafter. The question whether the Plaintiffs reside in the property and pay rental is a matter between the parties themselves to agree upon. What they must bear in mind is that the terms of the Deed apply to the circumstances of this case whether the property is rented by the Plaintiffs or not. I see no need therefore at this point of time to make any orders for the Plaintiffs to vacate the said property if they are in current occupation of the property.

class="MsoNormal" sal" style="tab-stops:92.25pt 120.75pt 281.25pt right 466.4pt; margin-top:1; margin-bottom:1">The second order sought in the counter-claim was for damages for breach of contract as specified in paragraph 4 of the affidavit of Lydia Yeo filed 4 October 1999. Sub-paragraph 4(a) sought orders for payment of half share of the insurance premium of $901-00. In his affidavit evidence filed 8th October 1999, at paragraph 2(b), Ellison Kiere deposed he had paid the amount of $1,600-00 towards the insurance premium for the property. No evidence in rebuttal had been filed. I am not satisfied on the balance of probabilities the order sought in respect of this claim should be granted.

lass="MsoBodyText"Text" style="margin-top: 1; margin-bottom: 1">The third order sought, for damages, as specified in sub-paragraph 4(b) r the amount of $23,267-00, being part of a loan obtaiobtained by the Defendant to off-set the non-payment of the $25,000-00. In my respectful view that claim is directly related to the breach of Sub-clause 4.1 and therefore judgment should be entered in favour of the Defendant. The Plaintiffs however are entitled to have the principal amount of that loan off-set from the amount of $25,000-00 still outstanding in the Deed.

class="MsoBodyText"Text" style="margin-top: 1; margin-bottom: 1">The fourth order sought pertains to rental payments claimed by the Defendant still owing. I have already set out in my judgement what the true position in law is between the parties The parties accordingly should work out between themselves what their position should be regarding rental payments received to date. Any outstanding matters may be raised by way of summons for chambers hearing.

The following orders in s in my respectful view should be made.

THE ORDE ORDERS OF THE COURT:

(A) CLAIM OF THE PLAINTIFF

1. DECLARE THE DEFENDANT HAD WRONGLY REPUDIATED THE DEED OF SALE DATED 9TH OCTOBER 1998.

2. CONSEQUENTIALLY DECLARE THE PLAINTIFFS ARE ENTITLED TO DAMAGES FOR WRONGFUL REPUDIATION TO BE ASSESSED IF NOT AGREED.

3. CONSEQUENTIALLY GRANT ORDER FOR SPECIFIC PERFORMANCE OF THE DEED OF SALE DATED 9TH OCTOBER 1998.

(B) COUNTER-CLAIM OF THE DEFENDANT:

1. REFUSE ORDER TO HAVE PLAINTIFFS VACATE PROPERTY THE SUBJECT OF THIS DISPUTE.

2. ENTER JUDGMENT FOR THE DEFENDANT FOR THE SUM OF $23,267-00, PAYABLE IN THIRTY (30) DAYS. THE PRINCIPAL AMOUNT OF THE LOAN IS TO BE OFF-SET FROM THE AMOUNT OF $25,000-00.

3. DECLINE ORDER FOR PAYMENT OF INSURANCE PREMIUM.

4. DECLINE ORDER FOR MESNE PROFITS.

(C) COSTS

THE APPROPRIATE ORDER FOR COSTS IN THE CIRCUMSTANCES OF THIS CASE IS FOR THE PARTIES TO BEAR THEIR OWN COSTS.

THE COURT


PacLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.paclii.org/sb/cases/SBHC/1999/113.html