Home
| Databases
| WorldLII
| Search
| Feedback
High Court of Fiji |
IN THE HIGH COURT OF FIJI
AT SUVA
CIVIL JURISDICTION
CIVIL ACTION NO.: HBC 18 of 2018
BETWEEN : JOJI DUVAGA
PLAINTIFF
AND : TEBARA TRANSPORT LIMITED
DEFENDANT
APPEARANCES/REPRESENTATION
PLAINTIFF : Ms Sauduadua [Lal/Patel/Bale Lawyers]
DEFENDANT : Mr Kumar with Mr Singh [Parshotam Lawyers]
RULING OF : Acting Master Ms Vandhana Lal
DELIVERED ON : 05 March 2020
INTERLOCUTORY RULING
[Setting Aside Judgment By Default]
The Application
The said application is made pursuant to Order 19 rule 9 and Order 45 rule 10 of the High Court Rules and is supported by at an affidavit of Arvind Maharaj.
Brief Chronology Of The File Prior To Filing Of The Said Application
His claim is for damages for injury he sustained whilst working as a heavy mechanical serviceman at the Defendant’s garage at Sealark Hill, Edinburgh Drive, Suva.
Was the Judgment so extend regular?
“A claim of damages on tort is a claim for unliquidated damages. It remains unliquidated until the amount has been fixed either by the judgment of the court or by an agreement as to be amount which must be paid satisfy the Claim”.
In the said case Singh J. stated that “the Plaintiff would need to prove his loss of income. He would need to show how much he was earning per day, where did he work, any tax and FNPF deductions”.
“There is therefore some scope for debate as to the width of the word "debt" in this context. As for the word "liquidated", I would take it that, in ordinary legal usage, this requires that the liability should be for an ascertained amount. Most liquidated claims would be for a debt. Obvious examples include the outstanding principal and unpaid interest (at a contractual rate) on a loan, and sums due by way of rent or hire, and the price of goods (if specified in the contract). Conventionally, unliquidated claims are normally in damages. Some damages claims, however, may be liquidated. A good example is a building contract which has a liquidated damages clause defining the builder's liability if the work is not complete by the stipulated finishing date. .............
In Amantilla Ltd v Telefusion plc (1987) 9 Con LR 139 His Honour Judge John Davies Q.C. sitting on Official Referees' Business held that a builders' claim for a quantum meruit was a claim within section 29(5). He said this on the point:
"If the parties themselves cannot agree on what is a reasonable sum, the contractual obligation to pay such a sum provides a sufficiently certain and definitive datum to enable the court to ascertain its amount by calculation and circumstantial (or "extrinsic") evidence, in accordance with the terms of the contract and without any further agreement of the parties. Indeed, it would be remarkable for the law to impose such an obligation if it did not have those attributes.
A quantum meruit claim for a 'reasonable sum' lies in debt because it is for money due under a contract. It is a liquidated pecuniary claim because 'a reasonable sum' (or a 'reasonable price' or 'reasonable remuneration') is a sufficiently certain contractual description for its amount to be ascertainable in the way I have mentioned ... Such a claim is different in kind from its opposite, which is a claim for unliquidated damages. The former is a claim for a specific sum, namely a reasonable sum due under a contract; it is no less specific for being described in words rather than in figures, provided it is sufficiently defined to be ascertainable - which it is, as I have already explained. The task of the court, if it has to assess such a sum, is one of translating the words of the contract into figures in order to effectuate the intention of the parties. The nature of a claim for unliquidated damages is wholly different. The function of the court is not one of interpreting the contract but of deciding, in accordance with legal principles, what compensation, if any, should be paid to redress any harm done by its breach. It is for these elemental reasons that a quantum meruit claim is a liquidated pecuniary claim, whilst conversely a claim for unliquidated damages is not, and cannot be such, even though it be claimed at a definite figure."
Final orders
..............................
Vandhana Lal [Ms]
Acting Master
At Suva.
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.paclii.org/fj/cases/FJHC/2020/816.html