![]() |
Home
| Databases
| WorldLII
| Search
| Feedback
High Court of Fiji |
THE HIGH COURT OF FIJI
AT SUVA
CIVIL JURISDICTION
Civil Action No. HBC 185 of 2014
BETWEEN : DELZEV LIMITED a limited liability company having its registered office at 364 Fostors Road, South Purrumbete, Victoria, Australia.
1ST PLAINTIFF
AND : FLINN SAWMILLS LIMITED a limited liability company having its registered office at c/- 1st Floor, Suites 8 & 9, Queensland Insurance Centre, Victoria Parade, Suva in the Republic of Fiji.
2ND PLAINTIFF
AND : WILSON INVESTMENT MANAGEMENT LIMITED a limited liability company having its registered office at 5 Andrews Avenue, Wellington, New Zealand.
DEFENDANT
BEFORE: Master Vishwa Datt Sharma
COUNSELS: Mr. Afzal Khan for the Plaintiff
Ms. Low for the Defendant
Date of Hearing: 14th November, 2016
Date of Ruling: 16th February, 2017
RULING
[Application to strike out the Plaintiff’s substantive Writ of Summons and Statement of Claim pursuant to Order 25 Rule 9 of the High Court Rules, 1988]
(A) INTRODUCTION
- The Court on its own Motion issued a Notice to the parties on 09th May, 2016, listed the matter for the parties to show cause why the case should not be struck out for want of prosecution or as an abuse of the process of the Court since no action was taken for a period of more than six (6) months.
- This Notice was issued pursuant to Order 25 Rule 9 of the High Court Rules, 1988.
- The Plaintiff filed its Affidavit to Show Cause on 16th June, 2016 and the Defendant filed his Affidavit Supporting the striking out on 26th July, 2016 and second Affidavit on 01st February, 2017.
- The application was heard with Written Submissions on 14th November, 2016.
- (B) THE LAW
- This application is issued pursuant to Order 25 Rule 9 of the High Court Rules 1988, which inter-alia states as follows:
“(1) If no step has been taken in any cause or matter for six months then any party on application or the Court of its own motion may list the cause or matter for the parties to show cause why it should not be struck out for want of prosecution or as an abuse of the process of the Court.
(2) Upon hearing the application the Court may either dismiss the cause [or] matter on such terms as may be just or deal with the application as if it were a summons for directions.’
“The power should be exercised only where the court is satisfied wither (1) that the default has been intentional and contumelious, e.g. disobedience to a peremptory order of the court or conduct amounting to an abuse of the process of the court; (2) (a) that there has been inordinate and inexcusable delay on the part of the plaintiff or his lawyers, and (b) that such delay will give rise to a substantial risk that it is not possible to have a fair trial of the issues in the action or is such as it is likely to cause or to have caused serious prejudice to the defendants wither as between themselves and the plaintiff or between each other or between and a third party.”
“The correct approach to be taken by the courts in Fiji to an application to strike out proceedings for want of prosecution has been considered by this court on several occasions.
“(7) The question that arises for consideration is what constitutes” intentional and contumelious default” (First Limb). The term “Contumely” is defined as follows by the Court of Appeal in Chandar Deo v Ramendra Sharma and Anor, Civil Appeal No, ABU 0041/2006,
Lord “Woolf” in “Grovit and Others v Doctor and Others” (1997) 01 WLR 640[1997] UKHL 13; , 1997 (2) ALL ER, 417, has discussed the principles for striking out for “Abuse of process” (The second ground in Order 25 Rule 9 (1)) as follows:
“The Court had power under its inherent jurisdiction to strike out or say actions on the grounds of abuse of process irrespective of whether the test for dismissal for want of prosecution was satisfied. Accordingly, since the commencement and continuation of proceedings with no intention of bringing them to a conclusion was itself sufficient to amount to an abuse of process which entitled the court to dismiss the action, it was not strictly necessary in such a case to established want of prosecution by showing that there had been inordinate and inexcusable delay on the part of the plaintiff which had prejudiced the defendant. It followed, on the facts that the deputy judge had been fully entitled to strike out the action. The appeal would therefore be dismissed.”
“It may be helpful to add a rider. During the course of his careful and comprehensive ruling the judge placed considerable emphasis on the judgment of the House of Lords in Grovit and Ors v Doctor [1997] UKHL 13; [1997] 2 ALL ER 417. That was an important decision and the judgment was perfectly right to take it into account. It should however be noted that Felix Grovit’s action was struck out not because the accepted tests for striking out established in Birkett v James [1977] 2 ALL ER 801; [1978] AC 297 had been satisfied, but because the court found that he had commenced and continued the proceedings without any intention of bringing them to a conclusion. In those circumstances the court was entitled to strike out the action as being an abuse of the process of the Court. The relevance of the delay was the evidence that it furnished of the Plaintiff’s intention to abuse the process of the Court.”
(C) ANALYSIS and DETERMINATION
Default is contumelious
In fact, neither any further action was taken by the Plaintiff after the pleadings were closed nor did this Court make any directions and orders for the parties to comply.
For the above rational, the first arm of the test does not apply herein since this court at this stage of the proceedings did not make any directions rather the set down procedure in law should have been adhered to. The Plaintiff after filing the Reply to the Statement of Defence and the Counter-Claim should have filed and served a Summons for Directions and sought the directions and orders of this Court to move the matter further, but failed to do so and let the matter remain pending in the system till now.
Delay
Intentional
For these two elements to be satisfied, the Defendant must establish that the delay was intentional on the part of the Plaintiff. In other words the Plaintiff has filed an action with having no intention to proceed with the same.
The Plaintiff submitted ‘that it had filed a notice of intention to proceed with the matter. The delay in progressing with this matter was due to related issues with this case which relates to the consent of the Minister for Lands to a dealing made between the First named Plaintiff and BSP Life (Fiji) Limited. Ministerial consent was being sought by the Plaintiffs to enable transfer of the property as such consent is time consuming to obtain. A letter dated 07th October, 2016 from the Ministry of Lands & Mineral Resources was sent to our office informing us that the Judgment on the property registered under CT 23022 needs to be withdrawn after which they would proceed with the Ministerial Consent application.’’
The Defendant submitted ‘that the Plaintiffs have failed to show cause and have not adequately explained or justified the extensive delay in prosecuting these proceedings. The Plaintiffs have also not taken any steps to otherwise progress with these proceedings or shown that they are ready or able to do so. Further delays will only serve to drag this matter out further and continue to prejudice the Defendant unjustifiably. Delay caused by the Plaintiff up to the time of service of Order 25 Rule 9 Notice is 11 months.”
The question then is whether delay alone is sufficient for the Court to strike out an action for want of prosecution. The Court of Appeal in the case of New India Insurance Co. Ltd –v- Rakesh Kumar Singh Civil Appeal No. ABU 0031 of 1996 emphasized ‘that while inordinate and inexcusable delay might be established, these factors alone were not on their own sufficient to warrant the striking out of the action.’
Further, the delay in the manner and circumstances described hereinabove was unintentional on the part of the Plaintiff. The Plaintiff’s conduct also did not tantamount to an abuse of the Court process because there was no intention of the Plaintiff not to pursue this case any further and or to bring this action to a conclusion. If the Defendant thought otherwise then the Defendant should have filed an appropriate application and sought for relevant Court orders appropriate in the circumstances but failed to do so.
Inordinate
This relates to the length of delay. The word ‘inordinate’ is defined in the Supreme Court Practice meaning ‘materially longer than the time usually regarded by the profession and courts as an acceptable period.’
The issue this Honorable Court is burdened with is whether the inordinate delay was so material that it gives rise to a substantial risk that it is not possible to have a fair trial of the pending issues in this action. The Plaintiff filed the Reply to the Statement of Defence and the Counter- Claim and the pleadings in this case were closed. The Plaintiff did not pursue the cause of action hereafter. The time calculated from the date of the filing of the last pleadings in terms of the Plaintiff’s Reply to the Statement of Defence and the Counter- Claim, and until the issuance of the Order 25 Rule 9 Notice on 09th May, 2016, adds up to 11 months.
If the Defendant encountered any delay on the part of the Plaintiff in pursuing with the cause of action, then the Defendant as parties to the proceedings should have filed and proceeded with an appropriate application for Court to decide rather than wait and only act once the court issued and served the Order 25 Rule 9 Application.
In the above circumstances, I am of the finding that both, the Plaintiff as well as the Defendant are to be blamed for contributing to this delay. The reason being that if the Plaintiff did not pursue or prosecuted his case any further, the Defendant could have moved the court further, forcing the Plaintiff to file and serve the respective consequent pleadings to complete the pleadings and the cause. If the Plaintiff still failed, then the Defendants should have taken the alternative steps provided for in the Rules, rather than wait for the Plaintiff to pursue his case further. This was also not done. It is the duty of the Plaintiff to prosecute his case diligently and in the interest of his client in terms of the set down rules and procedures of the Court and bring the litigation of the case to its conclusion as expeditiously as can be done.
The delay by the Plaintiffs is neither intentional nor contumelious. Further, the delay is not inordinate and is excusable taking into consideration the reasons and the explanation provided to this Court. I do not find any reason or risk that it is not possible to have a fair trial of the issues in this action at its earliest. In addition, the conduct of the Plaintiffs does not constitute an abuse of the process of this court.
Taking into consideration the Plaintiffs affidavit showing cause together with the written submission, I find that the Plaintiffs have satisfactorily explained their delay which is not inordinate but excusable in the given circumstances and therefore is acceptable to this court.
Factors relating to inordinate and inexcusable delay on their own are therefore insufficient to warrant the striking out of this action in terms of Order 25 Rule 9 application.
Prejudice
The Counsel for the Defendant submitted that ‘further delays will only serve to drag this matter out further and continue to prejudice the Defendant unjustifiably. The Defendant has stated the prejudice it has been encountering in paragraphs 26-28 of its affidavit in support of the notice. The Defendant has estimated that the cost of the damage to the Plant and Machineries during the recent cyclone Winston as circa $200,000 apart from the costs of defending this action thus far, in the sum of $6,500.’
The Plaintiff submitted that ‘the Defendant had filed and served his Statement of Defence and Counter-Claim after a delayed time frame of 2 months and 9 days. Added that the Defendant did not encounter any prejudice as they had removed the Plants and the Machineries from the said property which was given out to the third party on a short term lease agreement. The Plaintiffs have been informed that much of the Planetary and Machinery have been sold by the Defendant which has not been fully disclosed by the Defendant to this Court. The Plaintiffs are willing and able and have been ready to perform the covenants and obligations under the sale and purchase agreement. The Plaintiffs are the one who are prejudiced by the Defendant’s action. The Defendant has already obtained the deposit and enriched himself by purportedly selling the machinery to the third parties and is therefore in no way prejudiced.’
I have taken into consideration the submissions and the case authorities in terms of Prejudice.
The Plaintiffs filed the Writ of Summons together with the Statement of Claim on 07th July, 2014 claiming that the 1st Plaintiff and the Defendant on or about the 03rd April, 2013 entered into a Sale & Purchase Agreement where the Defendant as the Vendor had agreed to sell to the 1st Plaintiff, as purchaser, the Plant and Machinery as described in the Sale & Purchase Agreement for the sum of FJD $250,000 pursuant to the terms and conditions therein free of all mortgages, charges and encumbrances whatsoever. That the Defendant breached the Sale & Purchase Agreement and gave a cancellation notice to the 1st Plaintiff and in breach of the Agreement purported to sell/or part with possession of Plants and Machinery to third party.
The pleadings were closed once the Plaintiffs filed their Reply to the Statement of Defence and the Counter-Claim on 16th June, 2015. No further action or cause was taken by the Plaintiffs until this Court issued and served a Notice in terms of Order 25 Rule 9 of the High Court Rules, 1988.The delay in pursuing the case any further was for a period of over 11 months, which in the circumstances is not materially longer than the time usually regarded by the profession and courts as an unacceptable period. I have also taken on board what the Defendant had to state at paragraphs 26-28 of the Affidavit filed on 26th July, 2016. Bearing in mind the nature of the substantive claim and that the Action was commenced in July, 2014, I am of the view that this Court ought to make further directions in terms of directing the Plaintiff to file and serve the Summons For Directions and parties to the proceedings expeditiously completing the requirement and pleadings thereafter so that the matter can be heard and determined for once and for all.
Therefore, I find that the Defendant has not suffered any real or substantial prejudice since the substantive matter is yet to be heard and determined by the Court.
Interest of Justice
[15] A more fundamental difficulty for the Respondent is that the judge failed to make any finding at all on the final question to be asked when applying the Birkett v. James principles namely: ‘In view of the delays which have occurred, is a fair trial now possible?’ (Also case of Department of Transport v, Chris Smaller (Transport Limited [1989] AC 1197 refers.
‘The applicant must show that the plaintiff has been guilty of inordinate delay, that such delay is inexcusable, and that it has seriously prejudiced the defendant. Although these considerations are not necessarily exclusive, and at the end one must always stand back and have regard to the interests of justice, in this country, ever since NZ Industrial Gases Ltd v Andersons Ltd [1970] NZLR 58 it has been accepted that if the application is to be successful, the applicant must commence by proving the three factors listed.’
‘26. This principle was restated by the Court of Appeal of Fiji in Pratap v Kristian Mission Fellowship [2006] FJCA 41. Also refer to; New India Assurance Co Ltd v Singh [1999] FJCA 69.
The principle as enunciated in these cases reflects the principles on this topic in other common law jurisdictions. These decisions include; Metropolitan Bank Ltd v Pooley (1885) 10 App Cas 210; Dey v. Victorian Railway Commissioners (1949) HCA 1; (1949) 78 CLR 62; Birkett v James [1978] AC 297; Lovie v Medical Assurance Society Limited [1992] 2 NZLR 244; Agar v Hyde [2001] HCA 41; (2000) 201 CLR 552. Indeed the passage from Abdul Kadeer Kuddus Hussein v Pacific Forum Line reflects closely Birkett v James (above). These authorities also make the point that in exercising a peremptory power of the kind under contemplation in these proceedings, the court must be cautious and to put the matter in another way, the court must stand back and ensure that sufficient regard is ahead of the interests of justice.’
Dated at Suva this 16th Day of February, 2017
.................................................................
MR VISHWA DATT SHARMA
Master of High Court, Suva
cc: Khan & Company, Suva.
Howards Lawyers, Suva.
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.paclii.org/fj/cases/FJHC/2017/127.html