![]() |
Home
| Databases
| WorldLII
| Search
| Feedback
Court of Appeal of Fiji |
IN THE COURT OF APPEAL, FIJI ISLANDS
ON APPEAL FROM THE HIGH COURT OF FIJI
Civil Appeal No.ABU 0016 OF 2009
[High Court Civil Action: HBC 94 of 2004]
BETWEEN:
CHRISTIAN MISSION FELLOWSHIP
by its trustees Pastors Naibuka Gonewai, Sanaila Soqovata, Josaia Tokea,
Emosi Toroca Ratavola and Reverend Suliasi Kurulo
APPELLANTS
[Original Defendants]
AND:
WILLIAMS ASSOCIATES LIMITED
RESPONDENT
[Original Plaintiff]
CORAM : Hon. Justice Kankani Chitrasiri, JA
Hon. Justice Sosefo Inoke, JA
Hon. Madam Justice Anjala Wati, JA
COUNSEL : Mr. I. Fa for the Appellants
Mr. I. Roche for the Respondent
DATE OF HEARING : Friday, 2nd September 2010
DATE OF JUDGMENT : Wednesday, 21st September 2011
JUDGMENT
Kankani Chitrasiri, JA
speak to the matters agreed upon by the parties. Admitted facts bearing Nos. (3) and (4) read thus:
“(3) on or about 16th March 1998 the CMF through its servants, agents/employees engaged the services of the Plaintiff as Quantity Surveyors in respect of the World Harvest Centre Project at Kinoya, Nasinu.
(4) On or about the same date the Plaintiff and the CMF agreed on the fees payable in respect of services to be performed by the Plaintiff based on the Australian Institute of Quantity Surveyors Conditions or Engagement dated 1st January 1983.”
it is stated:
[Emphasis added]
Anjala Wati, JA
Sosefo Inoke, JA
13. This is an appeal from the judgment of Mr. Justice Hickie delivered on 13 February 2009
granting the respondent’s claim for outstanding fees for quantity surveying services provided for the building of the appellant’s
new church known as the “World Harvest Centre” at Kinoya, Nasinu. That judgment is reported in Williams Associates Ltd v. Gonewai [2009] FJHC 88; HBC94.2004 (13 February 2009).
to claim extra fees because the initial construction costs increased.
am not persuaded. The grounds of appeal do not cover an appeal on quantum and, in any event, I agree with the reasoning and findings of Hickie J and would not disturb his Lordship’s findings on quantum.
The Background
$5.2m.
extra fees of $77,081.55 based on calculations using the AIQS Conditions on the cost overrun.
outstanding on the initially agreed fee of $45,000.
Statement of Claim on 16 March 2004 claiming these outstanding and extra fees, interest thereon and costs.
The Issues
were part of the agreement based on the AQIS Conditions; and (b) whether the plaintiff performed those services.
The Findings of the High Court
“[72] Thus, it is the finding of this Court that the conditions of agreement as set out in the letters of 16 March and 13 February 1998, were that a fee of $45,000 was to be charged on TWO conditions:
(a) That the construction cost be $2million; AND
(b) That it was subject to the AIQS Conditions of Engagement dated 1 January 1983.
[73] Further, it is the finding of this Court that once the construction cost exceeded $2million, then it was covered by the AIQS conditions Clause 8.06.02, that is, “Where, after Bills of Quantities have been prepared, the Quantity Surveyor prepares amendments to the Bills additional fees will be charged on the amount of both measured additions and omissions in accordance with Scale of Fees Clause 6.01.”
respondent did do the work for the additional fees claimed. His Lordship also held that the appellants failed to meet the evidentiary proof required of it.
“[103] As a result of the above evidential findings, the Court concludes that in relation to the persuasive burden, the Plaintiff has established its case by a preponderance of evidence, that is:
(a) That it is entitled to $1,400 outstanding since 13 April 1999;
(b) That it is entitled to $400 outstanding since 28 May 2000;
(c) That it is entitled to $77,081.55 outstanding since 28 July 2000.”
$89,209.60 making a total of $172,505.22. His Lordship limited the interest component to what the respondents would be entitled to under the terms of the agreement. He held that the appellants were put on notice of the claim as early as 26 August 1999 with the account eventually rendered on 14 July 2000. He noted[4] that this was a matter which should have been resolved soon after it occurred or at least by the end of 2000, and, if not, then soon after the Statement of Claim was filed, rather than the plaintiff having to wait for nearly 10 years.
The Grounds of Appeal
fact and law in holding that the AIQS Conditions applied to the agreement between the parties thereby authorising the payment of extra fees based on the final construction cost of $5.2m.
Consideration of Submissions and Grounds of Appeal
respondent on the grounds that Mr Roche had worked for his law firm previously. Mr Roche was not involved in this case at the High Court or in the preparations for this appeal. Mr Fa’s objection was simply that Mr Roche had worked for his law firm in the past. Clearly, there was no basis for the objection so it was overruled.
have said at the outset, I am not persuaded that this ground, or any other ground for that matter, is in respect of quantum. In any event, I agree with the learned trial Judge’s findings that the plaintiff did provide the extra services for which it charged and the fee thus charged was calculated in accordance with the terms of the agreement, namely, the AQIS Conditions based on the final construction cost. I would not have allowed the appeal had it been an appeal against quantum.
of interest so the trial Judge’s findings and orders in this respect, with which I agree in any event, will not be disturbed.
charge extra fees if the construction cost escalated from $2m to $5.2m?
cost of $3.2m and not $5.2m.
“[66] In addition, apart from the Plaintiff being wrongly blamed for any perceived inadequacies of the Project Manager, similarly the Plaintiff cannot be blamed for the construction cost of the building. If it increased, the Plaintiff’s work increased and as such sought appropriate recompense as Counsel for the Plaintiff has also set out in his Submissions in Reply: “... the substantial increase from the initial cost of construction from $2million to over $5million directly impacts on the initial contract of service agreed to by the Plaintiff” and is covered by the AIQS conditions 8.06.02 “which binds the Defendants and include the payment of excess fees where the Surveyor prepares amendments to the Bills”.
[67] To be clear on this issue, Clause 8.06.02 states:
“Where, after Bills of Quantities have been prepared, the Quantity Surveyor prepares amendments to the Bills additional fees will be charged on the amount of both measured additions and omissions in accordance with Scale of Fees Clause 6.01.”
[68] The Defendants’ case was that whilst the Plaintiff’s work was subject to the AIQS Conditions of Engagement dated 1 January 1983, it was set at $45,000 (as reduced by them from the $60,000 figure quoted in the Plaintiff’s letter of 13 February 1998) and that although the construction cost went from $2million to over $5million “the variation in the construction cost did not vary the contract of service that was entered into between the parties” set at $45,000 for a $2million project. The problem with this submission is what does one do when the cost of the project exceeded at least double and a half the initial amount? Should the Defendants retain the benefits of a clear exploitation of the Plaintiff? Further, this submission does not deal with clause 8.06.02 of the AIQS Conditions of Engagement which, as the Plaintiff has correctly submitted “binds the Defendants and include the payment of excess fees where the Surveyor prepares amendments to the Bills”.
[69] No person was called as a witness on behalf of the Defendants either as an expert or a professional in this field (such as from the Fiji Institute of Quantity Surveyors) that the manner in which the Plaintiff had “gone about” the preparation of their final account whereby they prepared a new account for the entire “job” based on the new final construction cost was not the standard practice for a quantity surveyor and in accordance with the AIQS Conditions of Engagement dated 1 January 1983.
[70] In addition, no oral evidence was called from the Project Manager, EDWARD RUSHTON FIJI LIMITED, to testify their firm disputed this condition or their understanding of this condition or that it was not the standard practice for a quantity surveyor and in accordance with the AIQS Conditions of Engagement dated 1 January 1983. Indeed, a Jones v Dunkel (supra) type inference can be drawn that the uncalled evidence would not have assisted the Defendants’ case.
[71] Significantly, it was also never put to Mr NAIDU, as the Architect for the project, that there was something untoward in what was done nor that it was not in line with the general ”commercial” or “professional” practice in this field. All that was put to Mr NAIDU was that the other professionals involved did not do the same, that is, render new accounts.
[72] Thus, it is the finding of this Court that the conditions of agreement as set out in the letters of 16 March and 13 February 1998, were that a fee of $45,000 was to be charged on TWO conditions:
(a) That the construction cost be $2million; AND
(b) That it was subject to the AIQS Conditions of Engagement dated 1 January 1983.
[73] Further, it is the finding of this Court that once the construction cost exceeded $2million, then it was covered by the AIQS conditions Clause 8.06.02, that is, “Where, after Bills of Quantities have been prepared, the Quantity Surveyor prepares amendments to the Bills additional fees will be charged on the amount of both measured additions and omissions in accordance with Scale of Fees Clause 6.01.”
cannot be correct. Clause 6 of the AIQS Scale of Fees provides for “Post Contract Services.” Amendments to the bills of quantities cannot be finalised until the building is completed. It is only at that time could the final costs, including the quantity surveyors fees, be determined.
they agreed not to charge extra fees. The trial Judge rejected the argument. His observations of the appellants’ two witnesses who gave evidence on the point were that one was a “forgetful and unreliable witness” which was to “put it kindly” and the other was “evasive to say the least”.[6] This Court cannot on the face of those observations reject the learned trial Judge’s findings: Ali v. Ali [2009] FJCA 66; ABU0029.2006 (3 December 2009). The trial Judge has not made a “palpable and overriding error”: Delgamuukw v. British Columbia, [1997] 3 S.C.R. 1010: http://scc.lexum.umontreal.ca/en/1997/1997scr3-1010/1997scr3-1010.html.
asserting that it is entitled to extra fees because the respondent had represented to the appellants that the construction costs would not exceed $2m. The submission is based on a misconception of the responsibilities of a quantity surveyor. The quantity surveyor does not fix the construction costs. The quantity surveyor calculates the costs based on information given to him by the builder and the client, in this case the appellants. In any event, the point was not pleaded, and if pleaded, could not have arisen out of the facts because the agreement included the AQIS Conditions. Hickie, J was quite correct in dismissing the submission.
Costs
Justices Chitrasiri and Wati.
Kankani Chitrasiri JA
Orders
........................................................
Hon. Justice Kankani Chitrasiri
Justice of Appeal
.......................................................
Hon. Justice Sosefo Inoke
Justice of Appeal
.......................................................
Hon. Justice Anjala Wati
Justice of Appeal
[1] Para 12.
[2] At para 102.
[3] At para 103.
[4] At para 115.
[5] At paras 66 to 73
[6] At para 78.
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.paclii.org/fj/cases/FJCA/2011/45.html